March 9, 1923 -controversy
over location because of swampy conditions and no sidewalks on Lorne Avenue,
lot owned by Dr. Stuart Scott
-
May 10, 1923 - motion
by Dr. Boyd & Dr. Wilkinson that the name for the new school be Stuart
Scott Public School
-
May 21, 1923 - moved
by William Keith, seconded by A.J. Davis - That whereas the Public School
Board has applied to this council for the purpose of erecting a new public
school , Be it resolved that the By-Law Committee is instructed to introduce
a By-Law to raise by debenture the said sum of $55,000. Said debenture
to be payable in thirty years at rate percent of 5 1/2%. Adopted May 21,
1923. Second reading - August 20, 1923
-
Engineer's report for water work extension and
consider grading Lorne Avenue preparatory to placing sidewalk
-
Building : Architect
- Mr. O. E. Tench, Construction
Company - Richardson, Construction
Plans-same as Alexander Muir and King George Schools
-
Description: 3 small
rooms, principal's office, storeroom, staffroom, 6 room school - 3 rooms
on each of two floors, 2 basement playrooms, one for girls, one for boys,
red brick building with stone facings, basement walls above ground level,
cut stone facings west and south entrance
-
August 28, 1923 - LAYING
THE CORNERSTONE - Sir William Mulock, K.C.B.
was assisted by the Right Honourable William Lyon McKenzie King, Prime
Minister of Canada. Chairman of Board, J.R.Y. Broughton presided . Rev.
A.J. Mann offered prayer. Sir William Mulock used a silver trowel to put
the stone in place
-
June 20, 1924 Board Report
RECEIPTS
|
Town
|
$55,000.00 |
| Bank Interest |
$270.80 |
|
Total
|
$55,270.80 |
DISBURSEMENTS
| O.E. Tench(architect) |
$1900.00 |
| W.E. Richardson - Contract |
$37479.55 |
|
Wardrobes
|
$650.50 |
|
Extras
|
$467.08 |
| Freight on Blackboards |
$11.00 |
| Beaver Blackboards |
$239.29 |
| Harris & Mason (wiring) |
$275.00 |
| Gadsby & Irwin (heating) |
$1225.00 |
| R. Sutton ( hauling dirt) |
$15.90 |
| Globe (advertising) |
$29.70 |
| Contract Record |
$18.00 |
| Re-site |
$3084.76 |
| Interest - overdraft |
$2.97 |
| Cash in bank |
$9512.15 |
| TOTAL |
$55270.80 |
Three classrooms opened September, 1924
| Division 1 |
Miss Rogers |
Junior 4 |
36 pupils |
| Division 2 |
Miss Staunton |
Senior 2/Junior 2 |
35 pupils |
| Division 3 |
Miss Moore |
First Class |
28 pupils |
| Division 4 |
Miss Dow |
Primary |
32 pupils |
-
1955 - Howlett Construction Company -
Central Part, Office & four classrooms
-
1964 - South Wing - Gymnasium, offices and
4 classrooms
-
1972 - Joined with King George under one principal
-
1975 - Library and reconstruction of a classroom
for a new office and staffroom
-
1994 - Joined with J.L.R. Bell under one principal
-
1998(May) - 75th Anniversary Celebration
|